Date(s) |
Event(s) |
|---|---|
May 2004 |
State Board of Education (SBE) adopts evaluation criteria - at least 30 months before adoption |
June 2004 |
Publishers briefing on criteria |
September 2004 |
Commission approves final timeline |
February-September 7, 2005 |
Recruit Instructional Materials Advisory Panel (IMAP)/Content Review Panel (CRP) members |
September-December 2005 |
Commission recommends IMAP/CRP members to SBE |
November 2005-January 2006 |
SBE action on IMAP/CRP members |
January 10, 2006 |
Invitation to submit meeting |
March 1, 2006 |
Deadline for submission information |
March 27-30, 2006 |
IMAP/CRP training |
April 13, 2006 |
Samples submitted to reviewers and Learning Resource Display Centers (LRDCs) |
April 14, 2006 |
Price quote distribution to publishers |
June 14, 2006 |
Price quote receipt deadline |
June 14-16, 2006 |
Legal compliance (LC) review |
June 27, 2006 |
Publisher withdrawal deadline (7 working days before deliberations) |
June 30, 2006 |
LC citation notices sent to publishers |
July 10-13, 2006 |
Deliberations |
July 31, 2006 |
Publisher response to LC citations |
September 2006 |
Subject Matter Committee and Commission action on recommendations |
October 2006 |
Public display period (30 days) |
November 2006 |
SBE hearing/action on adoption |
December 2006 |
Post-adoption publishers briefing |
January 2007 |
Final printed resources submitted |